Power Feed A on Generator Supply

Incident Report for dataforest

Identified

During routine maintenance of the UPS array for the A Feed, a malfunction occurred in one of the UPS modules. As a result, the system switched to bypass mode (automatically as intended), and the A Feed is currently running on emergency power. There was no impact on the IT infrastructure at any time.
The datacenter operator is working with the the manufacturer to resolve the issue as quickly as possible and will switch back to normal operation once the issue is resolved.
Till then, power on the A feed is not redundant and depending on emergency power.
We will keep you updated on the progress.
Posted Apr 21, 2026 - 09:00 CEST
This incident affects: [Datacenter] firstcolo FRA4 (Facilites).